Concrete Driveways & Concrete Work in Los Altos: What to Expect
Concrete driveway installation in Los Altos runs $4,500 – $12,000 and takes three to five working days from demo to the day you can park on it. That window covers excavation, base compaction, formwork, the pour, and cure time, with an inspection slotted between the prep and the pour. Call (833) 988-3521 for a free on-site estimate. One thing we tell every Los Altos homeowner up front: on the tree-lined lots in 94022 and 94024, a protected oak can shape the pour before a single form board goes down, and that’s worth knowing before you pick a finish.
How a Concrete Driveway Goes From Demo to Drive-On

Concrete work rewards patience and punishes shortcuts, so the schedule below is the one we hold to. Each stage has a decision point, and we flag it so you’re never blindsided mid-pour.
Day 1: Site walk and layout
We mark the driveway edges, confirm slope for drainage, and check where the downspouts and utility runs cross the footprint. You decide the finish and edge style here, because both affect the framing. On sloped Los Altos lots, this is also where winter runoff gets addressed: the driveway has to shed water away from the garage slab, not toward it.
Day 1 – 2: Demo and excavation
Old concrete or asphalt comes out, and we excavate to depth for the base. For a standard residential driveway that’s typically 4 inches of compacted aggregate base under a 4-inch slab, thicker where a heavier vehicle parks. If there’s a failing subgrade, soft soil, or a tree root field, this is the stage that swallows a day and adds cost. We don’t discover it after the pour.
Day 2 – 3: Base prep, forms, and reinforcement
We compact the base in lifts, set forms to the layout, and place rebar or welded wire mesh. Drainage corrections happen now, not later. You’ll usually see the site inspected at this point if your job requires a permit, and we schedule that inspection so the pour isn’t held up.
Day 3: The pour
Concrete arrives, gets placed, screeded, floated, and finished. Control joints go in at planned intervals to control where the slab cracks, because concrete always cracks somewhere and joints decide where. This is the decision-heavy day: broom finish, exposed aggregate, or a stamped border. Once it starts curing, the finish is locked.
Day 3 – 5: Cure and drive-on
You can typically walk on it in 24 to 48 hours and drive on it in about seven days, longer if the weather turns cool. Cooler coastal mornings off the Santa Cruz Mountains side slow the cure, so we build that into the calendar and don’t rush it. We walk the finished edges with you and hand over care instructions.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Concrete Options You’ll Choose Between
Most of the money sits in the finish and thickness decisions, not in the concrete itself. Here’s the honest trade-off on each.
- Standard broom-finish slab: the sensible default for a driveway. Good traction, low cost, hides minor imperfections. It’s the base of the $4,500 – $12,000 range.
- Exposed aggregate: pebble surface that’s grippier when wet and hides tire marks. Adds roughly 10 – 20% because of the extra finishing steps and wash timing.
- Stamped borders and score lines: a decorative drainage-apron or border detail without turning the whole drive into a showpiece. A small upgrade, but it nudges the price up.
- Thickness and reinforcement: 4 inches is standard; 5 inches with rebar is the choice where an RV or heavy truck parks or where the base soil is marginal. This is the single biggest lever on longevity.
- Integral color: pigment through the mix rather than a surface stain, so it doesn’t wear off. Costs a bit more but ages better than topical color.
If your driveway is part of a bigger front-yard plan, the wider scope lives on our Driveway & Pavers in Los Altos page, and the finishing brands we like include Belgard for borders and hardscape transitions where the concrete meets pavers. And if this concrete work is really a step toward a garage conversion or a new unit, homeowners often pair this with ADU Site Prep & Utilities in Los Altos so the driveway pouring, trenching, and utility runs get planned together instead of twice.
What Concrete Driveways & Concrete Work Costs in Los Altos, CA

Expect $4,500 – $12,000 for a full concrete driveway in Los Altos, and $250 – $700 for a reseal on a job you’re trying to hold onto a little longer. Five things push you toward the high end:
- Size and shape: a long, curved drive with tight radiuses takes more forms, more time, and more waste than a straight rectangle.
- Existing condition: a clean tear-out is fast; a failing subgrade with roots underneath is slow and adds base material.
- Drainage work: regrading, a swale, or a trench drain to keep water off the garage adds cost but prevents a problem you’d pay to fix later.
- Finish and thickness: exposed aggregate, integral color, and a 5-inch reinforced slab all sit at the top of the range.
- Permit scope: if the job ties into a larger site or structural change, the permit review adds time, not necessarily dollars to the concrete itself.
A written estimate from us is line-itemed: tear-out, base, forms, reinforcement, the pour, the finish, and any drainage. Not included unless we say so: landscape repair around the edges, relocating irrigation lines, and stump grinding if roots are in the way. No-hassle upfront pricing means the number you see is the number you pay on the work we quote.
See the difference
Before
After
Before
After
Before
AfterWhat a Los Altos Lot Does to a Concrete Pour
Los Altos is mostly 1940s through 1970s single-story ranch homes on large, mature lots, many now rebuilt or expanded into modern two-story customs. That mix matters for concrete. On the older homes, you’re pouring over decades-old subgrade that has seen root growth, patched utility trenches, and possibly an old asphalt layer buried under the concrete; we find that more often here than on newer streets. Winter rains off the Santa Cruz Mountains fog layer are when grading and drainage mistakes show up, so a driveway that puddles at the garage in January is usually a base-and-slope problem, not a concrete problem. And the tree-protection reality is real: on the streets around the 94022 and 94024 core, a protected heritage oak can dictate how close the pour can come and where the base can be compacted, so we check the protected-tree setbacks and floor-area limits before we finalize a layout. Call (833) 988-3521 to have us walk your lot and flag it early.
Serving Los Altos, CA – Our Local Coverage Area
We serve Los Altos and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Concrete Driveways & Concrete Work in Los Altos

Plan on three to five working days from demo to finished pour, plus about seven days of cure before you drive on it. Cooler coastal mornings off the Santa Cruz Mountains side can stretch the cure, so we build that into the schedule rather than promise a date we can’t hold.
Often yes, especially when the job changes site grading or connects to a larger structural or drainage scope. A straight replace-in-kind sometimes doesn’t trigger one, so we check against the current city requirements before work starts and pull what’s needed. Ask on your estimate call and we’ll tell you what applies to your lot.
Yes, a driveway replacement usually happens without opening the house. What we do watch is where the slab meets the garage apron and foundation, so the new concrete and the existing structure tie in cleanly and water sheds away from both.
Most Los Altos concrete driveways land between $4,500 and $12,000, and a reseal runs $250 – $700. The high end reflects size, drainage corrections, a 5-inch reinforced slab, or an exposed-aggregate finish. Call (833) 988-3521 for an exact quote: estimates are free and line-itemed.
All of our work is covered by the 730-Day Done Right Promise: if it isn’t done right, we make it right, one of the longest workmanship guarantees in residential construction. Concrete’s natural hairline cracking at control joints is expected and built into the design; anything outside that, we stand behind in writing.
Get a Free Concrete Estimate in Los Altos
Concrete is a one-shot job. Once it cures, fixing it means tearing it out, so getting the base, slope, and thickness right the first time is the whole game. A free on-site estimate is the place to start: we walk the lot, check for protected trees and drainage, and hand you a line-item quote you can compare. For a full scoped project, our Driveway & Pavers service covers the wider work, and you’ll find all the surrounding jobs on our Los Altos service-area page. Call (833) 988-3521. A live person answers around the clock, and homeowners often pair a new driveway with Door Installation in Los Altos when the front-entry timing lines up. On the call, we’ll ask about your lot, your tree situation, and your finish, then schedule the walk-through.