Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled
New Detached ADU in Los Altos, CA: What It Takes and What It Costs
A new detached ADU in Los Altos usually runs $90,000 to $220,000 and takes 9 to 14 months from the first site walk to the final inspection. A standard 600 to 800 square foot one-bedroom unit sits near the middle of that range; a larger two-bedroom with a full kitchen, laundry, and upgraded finishes pushes toward the top. Most Los Altos lots have the room for a detached unit, and the real constraints are tree protection, height limits, and how much utility work the site needs. Call (833) 988-3521 to schedule a free on-site estimate.
How a New Detached ADU Gets Built, Stage by Stage

Every detached ADU project follows roughly the same arc. Here’s what actually happens, in order, so you know what to expect and what you’ll be deciding at each point.
Stage 1: Site walk and feasibility (week 1)
We walk the lot, measure setbacks, and check for protected trees, easements, and existing utilities. You decide where the unit goes and how big it can be. On Los Altos lots, this step often reshapes the whole plan because a heritage oak or a tight side yard moves the building envelope. We give you a written scope and a line-item estimate at the end of this stage.
Stage 2: Design and permitting (months 1 to 4)
Architectural drawings, structural engineering, and the permit submittal happen here. Tree-protection review and the city’s height and floor-area checks are the usual slow points, so we build that time into the schedule. You decide the floor plan, exterior materials, and roof pitch. Expect the permit review to run several weeks after submittal, longer if the tree report triggers a redesign.
Stage 3: Site prep and foundation (months 4 to 6)
Demo of any existing structure, grading, trenching for water, sewer, gas, and electrical, then the foundation pour. On sloped or mature lots, drainage and grading get extra attention because winter rains will find any weak spot. You decide utility routing and whether the unit gets its own meter or taps the main service. Inspections follow each phase before work moves on.
Stage 4: Framing, rough-in, and enclosure (months 6 to 10)
Walls go up, the roof goes on, and plumbing, electrical, and HVAC get roughed in before the walls close. This is the longest stretch and the one where weather matters most. Rough-in inspections happen before drywall. You confirm window and door selections here, and we install them, with brands like ES Windows or CGI available where the spec calls for them.
Stage 5: Finishes, final inspection, and handoff (months 10 to 14)
Drywall, flooring, cabinets, fixtures, paint, and exterior finish. Final inspections follow, then a walkthrough with you. You make finish choices in the earlier stages so there’s no scramble at the end. The 730-Day Done Right Promise covers the workmanship from handoff forward.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make for a Detached ADU
The decisions that shape both cost and how the unit feels to live in come down to a handful of categories. Here’s what you’re choosing between and the honest trade-off of each.
- Unit size and layout. A studio or one-bedroom at 500 to 700 square feet keeps costs down and fits smaller lots. A two-bedroom at 900 to 1,000 square feet costs more but rents or houses family better. The foundation, roof, and utility runs scale with footprint, so size is the single biggest lever.
- Structure and foundation type. A slab-on-grade foundation is the simplest and cheapest route. A raised or crawlspace foundation costs more but handles sloped lots and gives you a place for plumbing and utilities. On older Los Altos lots, the soil and grade often dictate this choice.
- Exterior cladding. James Hardie fiber-cement siding holds up well against the marine fog and dry summers and needs little upkeep. Stucco is common on the surrounding housing stock and blends in, but it can crack and needs periodic patching. Wood siding looks warm but demands repainting on a seasonal rhythm.
- Windows and doors. Standard vinyl windows keep the budget in check. Impact-rated or higher-spec units from Andersen, Pella, ES Windows, or CGI cost more but improve insulation and sound control, which matters if the unit sits near a busy street.
- Kitchen and bath finishes. Stock cabinets and mid-grade fixtures keep the number down. Semi-custom cabinets and stone counters push it up. You’ll spend most of your finish budget in these two rooms.
- Utilities and metering. Tapping the main service is cheaper; a separate meter costs more upfront but simplifies things if the unit will be rented long term.
What a New Detached ADU Costs in Los Altos, CA

Plan on $90,000 to $220,000 for a detached ADU in Los Altos. That range holds whether you’re building on a flat 94022 lot or a sloped 94024 parcel, though the variables below decide where you land.
- Size and complexity: a compact one-bedroom stays near the low end; a two-bedroom with a full kitchen and laundry climbs toward the top.
- Site condition: a flat, open lot is cheaper to build on. Slopes, mature trees to protect, or tight access for equipment add cost.
- Utility work: long trench runs, a new panel, or a separate meter all add to the number. Moving an existing service entrance costs more than tying into it.
- Material grade: stock finishes versus semi-custom cabinets, stone counters, and upgraded windows can swing the total by tens of thousands.
- Permit scope: a straightforward project clears review faster and cheaper than one that triggers tree-protection review or a height variance.
A written estimate from us lists each of these line by line, so you see exactly what’s driving the number. Included in that estimate: design coordination, permit submittal, foundation, framing, utilities, finishes, and inspections. Typically not included: landscape repair around the unit, furniture, and anything you add after the scope is signed. Upfront pricing means the number you see is the number you pay, and 0% financing for 18 months plus $1,000 off projects over $10,000 helps spread the cost.
See the difference
Before
After
Before
After
Before
AfterWhat Los Altos Homes Specifically Do to This Job
Los Altos is a low-density, tree-canopied Silicon Valley suburb where nearly every project is a remodel or a tear-down rebuild on a mature lot. That reality shapes a detached ADU more than anything else. On the tree-lined streets around the 94022 and 94024 core, a protected heritage oak in the rear yard can dictate the entire footprint of the unit, and the city’s tree-protection ordinance plus its single-story and height limits mean plans routinely get re-engineered around a tree before a permit is pulled. We see this constantly on the larger lots off streets like University Avenue and the quiet blocks near downtown Los Altos.
The surrounding housing stock is mostly 1940s to 1970s single-story ranch and Eichler-adjacent homes on generous lots. When we build a new detached unit on those parcels, the existing service panel, drainage, and grading often need attention first. Winter rains off the Santa Cruz Mountains side expose any weak drainage on sloped lots, so we grade and waterproof with the wet season in mind. Outdoor work like stucco and exterior paint gets scheduled into the long dry spells. Homeowners here are often tech professionals who want architectural quality and a clean, quiet job site, and we build the schedule around that expectation. We cover Los Altos and the neighboring cities of Mountain View, Sunnyvale, Cupertino, and Santa Clara.
Serving Los Altos, CA – Our Local Coverage Area
We serve Los Altos and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Los Altos

Most detached ADU projects take 9 to 14 months from site walk to final inspection, with permitting eating three to four of those months. The construction itself runs six to nine months depending on size and site conditions. Call (833) 988-3521 for a schedule built around your lot.
Yes, a detached ADU requires a building permit, and on tree-protected lots it also triggers tree-protection review. We handle the submittals and coordinate the inspections, and we don’t start until the permits are in hand. Call (833) 988-3521 to talk through what your lot will require.
Expect $90,000 to $220,000, with size, site condition, utility work, material grade, and permit scope deciding where you land. A written line-item estimate shows exactly what’s driving your number. Call (833) 988-3521 for an exact quote, and estimates are free.
Usually yes, because a detached unit has its own utility runs, and the main question is whether your existing service panel has the capacity to add them. If it doesn’t, a panel upgrade is the fix, and we price it into the estimate. Call (833) 988-3521 and we’ll check your service during the site walk.
Every ADU we build is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. That covers workmanship for two full years after handoff. Call (833) 988-3521 to ask what’s covered on your project.
Ready to Price Your Detached ADU in Los Altos?
A new detached ADU is a big commitment, and the right first step is a free on-site estimate. We’ll walk your lot, check for trees and utility constraints, and hand you a written line-item quote. If the project grows into a broader plan, that work sits under our Home Additions & ADU service, and homeowners often pair a new unit with a Concrete Driveways & Concrete Work in Los Altos or a Paver Driveways in Los Altos job to finish the approach. It’s part of a full project scope we can quote together if you want, and it’s all covered under our Home Additions & ADU in Los Altos umbrella. Call (833) 988-3521 to schedule your free estimate, and a live person answers around the clock.
Written by the team at Groundwork Construction Co.