ADU Site Prep & Utilities in Los Altos: What the Job Actually Costs
ADU Site Prep & Utilities in Los Altos runs $45,000 – $130,000, and the site-and-utility portion alone is usually a five-to-eight-week stretch of work that starts long before any framing goes up. That money covers grading, excavation, the utility trench, the new electrical service, water and sewer tie-ins, and the drainage that keeps a sloped Los Altos lot dry through winter. Call (833) 988-3521 and we’ll walk your lot and give you a written line-item number, free.
Stage by stage: how site prep and utilities come together

Most homeowners picture the walls going up, but the part that determines whether the project survives its first rainy season happens in the ground. Here’s the real sequence, roughly how long each stage runs, and what you’re deciding at each point.
1. Site survey, staking, and utility locate (days 1 – 3)
We start by staking the actual footprint and calling for a locate on every buried line: gas, water, electric, sewer, and any irrigation the previous owner ran. On a mature Los Altos lot this is where we find the surprises, like a sewer lateral from 1962 that never got mapped or a roots-heavy line running right where the ADU needs to sit. You decide the final setback from the property line here, and if a heritage tree is anywhere near it, that conversation happens now, not after excavation.
2. Demolition, clearing, and grading (days 3 – 10)
Out come the old patio, the shed, the dead lawn, and any concrete that’s in the way. Grading follows, cut to the elevation the foundation plan calls for. On the sloped lots common off the Santa Cruz Mountains side of Los Altos, this stage often grows because winter drainage has to be designed in from the start. You’ll sign off on the finish grade before we form anything.
3. Excavation, trenching, and drainage (days 8 – 20)
This is the heaviest stretch. We trench for water, sewer, gas, and electrical conduit in one coordinated pass, then set the French drains, area drains, and the yard drain that ties to the storm system where the city allows it. The decision point: whether the sewer tie-in runs to the main at the street or connects to an existing lateral. The street tie can add serious money and weeks of coordination with the city.
4. Utility rough-in and inspection (days 18 – 35)
New conduit, a dedicated subpanel or full service upgrade, water line, sewer line, and gas run all get installed and then inspected before backfill. Nothing gets buried until the inspector signs off. You’ll pick your electrical service size and panel location here, and that choice depends on whether the ADU will have its own meter or sub-meter off the house.
5. Backfill, compaction, and final grade (days 32 – 45)
We backfill in lifts, compact to spec, and restore the yard to final grade so the slab or pier system can start on solid ground. You approve the finished surface and the drainage flow direction before we hand the site to the foundation crew. This is also when we coordinate anything else you’re doing outside, since homeowners often pair this with Concrete Driveways & Concrete Work in Los Altos while the equipment is already on site.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll actually make
- Utility trench method: open trench is cheaper and faster but tears up the yard; directional boring costs more and leaves the lawn intact. On a tight Los Altos lot with a protected tree, boring is often the only option.
- Electrical service: a dedicated meter panel runs more than sub-metering off the house, but it keeps the ADU independently billable and easier to rent. Sub-metering is cheaper up front and simpler to permit.
- Drainage: basic French drains and grading handle most mild-slope lots; a full yard drain tied to the storm system costs more but is what actually holds up through a wet January.
- Sewer connection: tying to an existing lateral is the budget path; a new street tie means city coordination, trenching under the sidewalk, and a much bigger line item.
- Foundation interface: a slab is the economical choice on flat ground; a pier-and-beam or raised system costs more but suits sloped lots and lets you route utilities underneath cleanly.
What ADU Site Prep & Utilities costs in Los Altos, CA

Site prep and utilities for a detached ADU in Los Altos land between $45,000 and $130,000, and where you fall in that band comes down to five things. First, lot slope: a flat lot grades cheaply, a sloped one needs retaining and engineered drainage. Second, distance to the utility mains, since every extra foot of trench and conduit adds cost. Third, whether you need a street sewer tie versus an existing lateral. Fourth, grade of drainage and electrical systems, from basic to full storm-tie and dedicated service. Fifth, permit scope, because tree-protection review and utility coordination both add time and fees.
A written estimate from us itemizes grading, trench length, utility runs, drainage, inspection coordination, and restoration separately, and the number you see is the number you pay. What it typically does not include: the foundation itself, the ADU structure, and finish work, which live on the wider Home Additions & ADU in Los Altos scope. Compare that to full Home Additions & ADU budgets and you’ll see site work is the foundation of the whole number, not an add-on.
See the difference
Before
After
Before
After
Before
AfterWhat Los Altos lots specifically do to this job
Los Altos isn’t a subdivision town, it’s a tree-canopied Silicon Valley suburb where nearly every project is a rebuild or addition on a mature lot, and that changes site prep in ways a new-build lot never sees. Across 94022, 94024, and 94023, a protected heritage oak in the rear yard can dictate the entire footprint of the ADU before a single permit is pulled, and Santa Clara County’s heritage-tree ordinance plus the city’s single-story and floor-area limits mean we routinely re-engineer trench routes and drainage around a tree’s root zone. The housing stock, mostly 1940s-to-1970s ranch homes, often needs a panel or service upgrade and a fresh sewer lateral because the originals weren’t built for a second dwelling. Winter rains expose grading and waterproofing problems on sloped lots, so drainage design gets locked in early. We cover the whole of Los Altos and the surrounding streets, and we know what the inspectors here look for.
Serving Los Altos, CA – Our Local Coverage Area
We serve Los Altos and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked: ADU Site Prep & Utilities in Los Altos

Plan on five to eight weeks from staking to final grade, with utility inspection the variable that most often adds days. Call (833) 988-3521 for a schedule built around your lot.
Yes. Grading, drainage, electrical service, and sewer tie-ins all require permits and inspections in Los Altos, and the utility work can’t be buried until it’s signed off. We pull and coordinate the permits as part of the job.
Often yes, if the ADU footprint aligns with existing mains and the sewer lateral is in usable condition. When a heritage tree or a shallow main forces a re-route, we tell you before excavation, not after.
Between $45,000 and $130,000 depending on slope, trench distance, sewer tie, and drainage grade. Call (833) 988-3521 for an exact quote: estimates are free and written line-item.
Every project is backed by our 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If something isn’t right, we make it right. Homeowners often pair the utility work with Paver Driveways in Los Altos while the yard is already torn up.
Get a free on-site estimate
Site prep is the part of an ADU you can’t afford to guess at, and a free on-site estimate is where it gets clear. Call (833) 988-3521 and a live person answers, day or night. We’ll walk your Los Altos lot, flag the tree and drainage issues up front, and hand you a written line-item number with no change-order surprises.
Written by the team at Groundwork Construction Co.